County Road 82: Upcoming Road Construction
Road construction on County Road 82 will begin soon. This will involve the milling and overlay of County Road 82 from County Road 21 to County Road 17, curb and storm sewer repairs, and installation of a new traffic signal at Stemmer Ridge Road/Mystic Lake Blvd./County Road 82. Please be aware of the following closures and lane restrictions and plan your route accordingly.
May 5-June 13 | County Road 82 Lane Closures From County Road 21 to Mystic Lake Blvd./Stemmer Ridge Rd
- At least one lane will remain open in each direction at all times.
- Access to intersections will be maintained.
May 5-June 19 | County Road 82 CLOSED From Mystic Lake Blvd./Stemmer Ridge Rd to County Road 17
- The intersection of County Road 82, Mystic Lake Blvd., and Stemmer Ridge Rd will remain open.
- Access from County Road 17 to homes on the west end of County Road 82 will be maintained.
- Access to the SMSC Water Treatment Plant will be maintained.
- The west entrance into Dakotah! Sport and Fitness will be closed.
- A traffic signal will be installed at the Stemmer Ridge/County Road 82 intersection.
June 16-18 | County Road 82 CLOSED From County Road 83 to Mystic Lake Blvd./Stemmer Ridge Rd
- Emergency vehicle access will be maintained.
- The intersections of County Road 83/County Road 82 and Stemmer Ridge/Mystic Lake Blvd. will remain open.
June 22-26 | County Road 82 CLOSED From County Road 21 to County Road 83
- Local access will be maintained for the Dakota Development Complex, SMSC Water Bottling Facility, Water Reclamation Facility, and the Tewapa neighborhood.
- Orion Road north of the Water Reclamation Facility will be closed during this period.
July 21-29 | Final Work (Striping and Sealing)
- No closures scheduled, but please be aware crews will be working in the area.
We appreciate your cooperation and understanding as we work with Scott County to complete these improvements.